Structural Steelwork Specialists

Client: Knowsley Borough Council
Main Contractor: Balfour Beatty
Engineer: Faber Maunsell
Architect: Aedas
Steel Tonnage: 6,000 t (approx)

Knowsley’s Building Schools for the future (BSF) programme is seeing the creation of seven new centres for learning, which will replace the 11 existing secondary schools in the area over a three year period.

Robinson Steel Structures were appointed in a partnering agreement with BBCL to supply deliver and erect the structural steelwork consisting of open, hollow and fabricated sections to the seven new learning centres. Robinson were also appointed to procure the pre-cast flooring, pre-cast stairs, and pre-cast lift shafts for the projects.

Built on the sites of existing schools in the Knowsley area, Robinson Steel Structure’s ability to perform was critical in order to meet the challenging programme requirements of each of the seven new learning centres. Robinson Steel Structures state of the art fabrication facility was supplying and erecting fabricated steelwork to three of the learning centre sites concurrently at the peak of Robinson’ activity on these complex projects.

Robinson Steel Structures is committed to working with the project team towards the efficient delivery of projects aided by their innovative and flexible approach. Robinson Steel Structures are proud of their integral structural involvement in these state-of-the-art learning centres that will undoubtedly bring about sustainable change and enhancement for the future schooling in the knowsley area.